Case Study: Water
Project: AMP 4 Framework
Location: Warwickshire, Worcestershire, Birmingham and Gloucestershire
Client: Severn Trent Water
Contract value: £112m
Start: April 2005 Completion: April 2010
Brief Description
This framework involves the upgrade, modification and enhancement of Severn Trent’s water and sewerage treatment facilities across Warwickshire, Worcestershire, Birmingham and Gloucestershire, involving projects from £150k to £40m. Morgan Est’s multi-disciplinary teams provide mechanical, electrical and civil engineering services to deliver projects through all their phases of design, construction, installation and commissioning. The framework is based upon a collaborative alliance approach and enables all parties to share best practice and continuous improvement initiatives, delivering consistent best value. The framework runs until 2010.
» More Case Studies